Module Preparation

When a module arrived SR1, several preparation work were done before the module was installed into the barrel.
o

The tasks includes:

o Capacitor installation (~1-2 days/module)
o Insert capacitors
o Check capacitor connectivity
o Check HV traces
o HV test: caps + wires
o Seal capacitors
o
o Pre-insertion prep. (6 modules/day/2 person)
o Check ground wire
o Check cooling sleeve
o Check mounting holes
o Active gas fittings, custom made for each module: connection & leak test
o o
o Glue purging gas gasket
o Tape HV kapton for protection
o Glue thermal sensors as needed (4 modules each type)